Setting 14,000 lb chiller units inside of hanger.
Project Challenges: This project was done inside of the hanger and only had 45 feet of head room and other crafts working in area. Rigging was a problem using a spreader bar and still keeping the proper angle of the rigging. Once units were loaded onto second floor we had to jack and roll them into place.