CADRE SAND PLANT


Building new sand plant. Install shaker, unloaded shaker covers and installed six, 80ft to 90ft conveyors on second level of structure.

Project Equipment: Tadano ATF-110G-5

Project Challenges: Long reach to pick, long reach to install up over and through structure with a lot of rigging. Very busy job site with a lot going on.